N&S Washington Ave. Paving Update

N&S Washington Ave. Paving Update

July 9th: Tilcon will begin milling Washington Ave beginning at the Teaneck border at 3am and will work until 3pm in an effort to try and have New Bridge opened before Rush Hour.

July 10th: Mill – work from 7am to 5:30pm

July 11th: Mill – work from 7am to 5:30pm

July 12th: Mill – work from 7am to 5:30pm

July 13th: Mill – work from 7am to 5:30pm (End)

July 16th: Tilcon will begin paving operations at 3am at the Teaneck border. In this instance they will not be able to open the roadway due to curing.

July 17th: Pave – work from 7 am to 5:30pm

July 18th: Pave – work from 7 am to 5:30pm

July 19th: Pave – work from 7 am to 5:30pm (End)

July 23rd: Striping

July 24th: Striping

July 25th: Striping (End)

*This schedule is subject to additional changes due to inclement weather. Please note that the other upcoming roads will not be as challenging as Washington Avenue.

2018-07-02T21:12:57+00:00July 2nd, 2018|0 Comments